| Architectural Desktop 2004 Standard Wall Component Cleanup Priority Numbers | ||
| Wall Component Name | Priority | Comments | 
| Unnamed (Standard Wall) | 1 | Not a great number to start with - used with elevator | 
| Concrete (including footings) | 200 | |
| Concrete Masonry Unit (CMU) | 300 | |
| Air Gap (CMU) | 305 | |
| CMU Veneer | 350 | |
| Precast Panel | 400 | |
| Rigid Insulation (Brick) | 404 | |
| Wood/Metal Stud | 500 | |
| Air Gap (Stud) | 505 | two odd cases were found | 
| Insulation (Rigid and General) | 600 | type of insulation tends to vary | 
| Air Gap (Typical) | 700 | |
| Brick Veneer (Structural) | 800 | |
| Rigid Insulation | 804 | cases found with Brick Styles | 
| Air Gap (Brick) | 805 | |
| Brick and Brick Veneer | 810 | |
| Siding | 900 | didn't find a case of this but sounds good | 
| Metal Panel | 1000 | didn't find a case of this but sounds good | 
| Stucco | 1100 | didn't find a case of this but sounds good | 
| Glass | 1200 | didn't find a case of this but sounds good | 
| Gypsum Wallboard (GWB) | 1200 - 1230 | Increments of 10, varies when doubled up | 
| Bulkhead | 1800 | |
| Casework - Upper | 2000 | actual component name is "Case Top" | 
| Casework - Base | 2010 | Full Body without a toe kick | 
| Casework - Counter | 2020 | |
| Casework - Backsplash | 2030 | |
| Partitions (Bathrooms) | 3000 | Embeded in Multi-View Blocks | 
| Architectural Desktop 3.3 Standard Wall Component Cleanup Priority Numbers | ||
| Wall Component Name | Priority | Comments | 
| Unnamed (Standard Wall) | 1 | Not a great number to start with | 
| Partitions (Bathrooms) | 55 - 80 | Embeded in Multi-View Blocks | 
| Concrete | 200 | |
| Concrete Masonry Unit (CMU) | 300 | |
| CMU Veneer | 350 | |
| Brick Veneer (Structural) | 400 | |
| Rigid Insulation (Brick) | 404 | |
| Air Gap - Brick | 405 | |
| Brick Veneer | 410 | |
| Air Gap (Stud) | 499 | two odd cases were found | 
| Wood/Metal Stud | 500 | |
| Rigid Insulation | 600 | |
| Air Gap - Typical | 700 | |
| Gypsum Wallboard (GWB) | 1200 - 1230 | Increments of 10 | 
| Bulkhead | 1800 | |
| Casework - Upper | 2000 | |
| Casework - Base | 2010 | Full Body without a toe kick | 
| Casework - Counter | 2020 | |
| Casework - Backsplash | 2030 | |